Skip to content
Law

How to settle a contractor's claims after withdrawal from a work contract?

The general basis for the withdrawal from a contract (not only) for work is Section 2005 of Act No. 89/2012 Coll., the Civil Code, as amended (hereinafter referred to as the "Civil Code"), according to which the withdrawal from the contract terminates the rights and obligations of the parties to the extent of its effects. In accordance with Section 2004(1) of the Civil Code, the rights and obligations of the contractor and the client are extinguished from the outset.

Book cover titled "Neztrácejte čas se smlouvami" by ARROWS, offering practical legal tips.

Key takeaways

Following withdrawal from a contract for work, you are entitled to the return of what you have performed. The other party is obliged to surrender this performance to you, as stipulated in Section 2993 of the Civil Code.
The surrender of performance after withdrawal from a contract may not always be possible, for example, in the case of already constructed foundations for a family house. In such cases, the economic feasibility of the return is assessed to prevent the depreciation or destruction of the item or to avoid further dismantling costs.
If it is not possible to return the performance, the contractor is entitled to monetary compensation. This applies, for instance, when the contractor has laid flawless foundations that can be used by another supplier to complete the construction.
The amount of monetary compensation is determined based on the onerous nature of the contract for work. Given that a contract for work is by definition always onerous, the compensation will be based on the value of the work performed.
ARROWS law firm

Rights and Obligations After Withdrawal from a Contract

If one of the parties has already performed under a contract for work and the contract is withdrawn from, that party has the right to the return of what it has performed, and the other party has the obligation to hand over this performance. For example, if the client has already paid a deposit and the contract for work is withdrawn from before the contractor has begun the agreed work, the contractor is obliged to return the deposit paid by the client.

If the contractor and the client have already performed for each other (e.g., the contractor has already built the foundations of a family house, and the client has already paid a deposit), then each party has the right to demand the return of what it has performed (Section 2993 of the Czech Civil Code), and the other party has the obligation to hand over the performance. 

To Return the Performance, or Not? That Is the Question

In practice, however, it is not uncommon to encounter a situation where it is not reasonably possible to return the performance that is being requested. For example, if a contractor is obliged to hand over the performance they have carried out in the form of the constructed foundations of a family house, it can be argued that it is not reasonably possible to hand over this performance. 

When assessing whether it is possible to return a performance or not, the economic consequences of returning the performance must be considered in particular. Therefore, the return of the performance should not lead to:

(i) the degradation or even destruction of an item that could otherwise serve its purpose where it is located (installed), 

(ii) further costs that would need to be incurred for the dismantling of the item being returned.

When Does a Claim for Monetary Compensation Arise?

If the client withdraws from the contract for work, for example, due to a delay on the part of the contractor, and the contractor has already laid the foundations of the family house, which show no defects and can be used for their purpose by another contractor who takes over the construction of the family house, then it can be concluded that the return of the subject of performance is not reasonably possible. If a court concludes that the return of the performance is not reasonably possible, the contractor is entitled to monetary compensation.

DO YOU NEED LEGAL HELP?

Get in touch — we're happy to help.

ARROWS law firm

What Will Be the Amount of Compensation?

When determining the amount of monetary compensation, it is necessary to consider primarily whether the contract was for consideration or gratuitous. Since a contract for work is by definition for consideration, monetary compensation is primarily provided in the amount of the relevant price agreed in the contract (Section 2999(2) of the Czech Civil Code). Therefore, if a deposit was paid in the amount of the price agreed for the foundations of the family house (e.g., as part of the budget), then the contractor who built the foundations free of any defects is entitled to reasonable compensation in the amount corresponding to the deposit after withdrawal from the contract.

If the amount of the price itself was the reason for withdrawal from the contract, or if the amount of the price was substantially influenced by such a reason, or if, for example, a contract for work was agreed but the price was not, then after withdrawal from the contract, the contractor would be entitled to monetary compensation in the amount of the market price of the performance provided (the market price for the constructed foundations of the family house), usually determined on the basis of an expert report. It would therefore be necessary to base it on the price that would have been achieved by selling this performance carried out by the contractor at the given place and time (by selling the foundations of the family house).

Defective or Incomplete Performance? Compensation Must Be Reasonable

When determining reasonable compensation (in the amount of the price for the performance agreed in the contract or in the amount corresponding to the market price of the performance), it is also necessary to take into account any defectiveness or incompleteness of the performance provided, if such defectiveness or incompleteness would justify a reduction in the value of the performance (the constructed foundations).

Depending on the circumstances, the contractor would thus be entitled to reasonable compensation after withdrawal from the contract corresponding to:

(i) the market price of the constructed foundations, where in determining this price, the expert would also have to take into account the defects of these foundations, or

(ii) the price agreed in the contract for the completed part of the work that is not reasonably possible to return to the contractor, where this price would be reduced by an amount corresponding to the client's claim for a reasonable discount due to the defectiveness of the completed foundations.

Are you planning to conclude a contract for work? We have prepared a webinar for you where you will learn all the key information for drafting and managing this type of contract.

Why Choose Us?

Our services are used by companies of all sizes because we provide them with fast and effective solutions in the field of contractual documentation. For example:

  • Customised contracts without unnecessary delays: We will prepare commercial contracts, agreements with suppliers, employment contracts, and other documents to meet your needs and minimise risks.

  • Clear and understandable terms: We design contracts to be practical, clear, and easy to use in day-to-day operations.

  • Protection against legal complications: We help clients avoid ambiguities, disputes, and unfavourable conditions.

About the author

JUDr. Lukáš Dořičák, LL.M., MBA
JUDr. Lukáš Dořičák, LL.M., MBA

Associate

Lukáš Dořičák graduated at Palacký University in Olomouc, Faculty of Law. During his studies he worked both in a small law firm specialised in general practice, and then in a prominent Czech law firm where he gained valuable experience especially in the field of corporate law. Lukáš developed his theoretical knowledge as a chairman of the editorial board of the technical journal lurium Scriptum.

Disclaimer:

The information contained in this article is for general informational purposes only and serves as a basic guide to the issue as of 2026. Although we strive for maximum accuracy, laws and their interpretation evolve over time. We are ARROWS Law Firm, a member of the Czech Bar Association (our supervisory authority), and for the maximum security of our clients, we are insured for professional liability with a limit of CZK 350,000,000. To verify the current wording of the regulations and their application to your specific situation, it is necessary to contact ARROWS Law Firm directly (consultation@arws.cz). We are not liable for any damages arising from the independent use of the information in this article without prior individual legal consultation.