Legal Framework and Risk Management for Real Estate Development in Czechia

A real estate development project involves dozens of legal steps, from site assessment and demanding permitting processes to the final sale of units. Each phase carries risks that can jeopardize your investment or lead to litigation in Czech courts. In this article, we will demonstrate how the correct legal framework protects your project and why it pays to cooperate with our Prague-based attorneys who handle these matters daily under Czech legislation.

The photograph depicts attorneys consulting on the legal framework for real estate development projects.

Quick Summary

  • Legal due diligence of land is the foundation of success: A proper assessment of zoning availability and legal defects in the Czech Republic will determine whether the project is feasible.
  • Financing requires precise contractual architecture: Loan documentation with the bank must be set up to avoid deadlocks and covenant breaches under Czech commercial law.
  • Sale of units and taxes must be handled conceptually: The VAT regime, the definition of building land, and exemption periods are matters that our Prague-based attorneys address strategically.
  • Significant penalties loom without professional legal oversight: Czech authorities can impose high fines, and buyers may claim discounts or damages.

Legal Assessment of Land: The First Decisive Step

Land acquisition is usually driven by business logic—you see a suitable location and want to close the transaction. However, the reality is more complex, and a development acquisition is not a standard real estate purchase. It is a collision of legal, zoning, and economic factors that determine the viability of the entire project in the Czech Republic.

Legal due diligence of the land is a critical step that goes beyond mere verification of ownership. It involves a detailed analysis of the legal status, environmental liabilities, compliance with the local zoning plan, and verification of utility infrastructure.

Compliance with the Building Act and Zoning Plan

The new Czech Building Act No. 283/2021 Coll., which became fully effective on July 1, 2024, brought significant changes to building permits and spatial planning. The municipal zoning plan is a binding document that defines the functional use of areas and spatial regulations.

Developers must strictly distinguish between "buildable area" and "building land" within the meaning of implementing regulations and the Czech VAT Act. For a developer, this distinction is crucial as it affects both the permitting process and the tax regime of the transaction.

Czech law requires project documentation to comply with current standards. Carrying out construction in violation of a permit can lead to fines in the millions of CZK and, in extreme cases, orders for the demolition of the structure. An error in the initial assessment of the project's compliance with the zoning plan can thus prove fatal.

Practical Advice: Never rely solely on the seller's claim that the land is "buildable." Always request official zoning information and have the limits of land use verified by our Czech legal team.

get in touch with us,
we’ll take care of it for you

Easements, Encumbrances, and Hidden Rights

During due diligence, easements (servitudes) often emerge, such as utility rights for pipes running across the land, rights of way, or pre-emptive rights.

In practice, our law firm in Prague often handles cases where a developer was surprised by an unregistered easement or a utility protection zone. These obstacles can often be resolved contractually, for example, by relocating utilities, but this requires timely negotiation.

Historical mortgages or "notices of dispute" in the Czech Land Registry are also common risks. A bank will not finance a project unless it is certain of the clarity of the legal title. ARROWS performs a detailed analysis of acquisition titles up to 10 years back to eliminate the risk of future ownership challenges.

Environmental and Geological Risks

Legal audits must also reflect the physical state of the land, as soil contamination can result in remediation costs in the millions of crowns.

If protected habitats are located on the site or if the land is in a flood zone, obtaining a Unified Environmental Statement (JES) can be complicated. Our attorneys in Prague work with experts to ensure that risks uncovered by surveys are reflected in the purchase agreement.

get in touch with us,
we’ll take care of it for you

MicroFAQ

1. What happens if I discover a defect in the land only after the purchase?
If it is a defect that the seller knew about and concealed, or if they breached their representations, you are entitled to a price reduction or withdrawal from the contract. It is vital to claim the defect within the statutory or contractual deadlines under Czech law.

2. Is a "good location" a guarantee that I can build on the land?

No. Even a plot in the center of Prague may be designated in the zoning plan as green space or public amenities, where residential construction is not permitted. It is always necessary to verify the zoning regulations.

3. How long does legal due diligence take?
A basic report can be prepared within one week. A complete in-depth audit usually takes 2–4 weeks depending on the complexity of the legal relationships and the availability of documentation.

Contractual Security for Building Rights and Land Acquisition

An alternative to direct land purchase that saves cash flow at the start of a project is the "Right of Build" (právo stavby). This is a real right under the Czech Civil Code that allows a structure to be owned on someone else's land, whereby the land and the building are legally separated.

The developer agrees with the owner on the establishment of the right of build and pays a "building fee." This solution is suitable in situations where the owner does not want to sell the land but agrees to construction.

Future Purchase Agreement

Developers often enter into a Future Purchase Agreement (SOSBK), which serves to reserve the land while the developer processes the project permits.

The SOSBK must be precise, as vague definitions of the land or conditions lead to invalidity. Key points include the specification of the real estate, the purchase price (fixed or formula), the deadline for closing, and resolutive conditions in case permits are not obtained.

Negative Covenants and Seller Representations

In transaction documentation, representations and warranties are essential, where the seller confirms that the land is not burdened by debts or litigation in Czech courts.

If a representation proves to be false, the developer is entitled to compensation. Our Prague-based law firm standardly sets these representations to provide maximum protection for the client's investment.

get in touch with us,
we’ll take care of it for you

MicroFAQ

1. What is the difference between a Future Purchase Agreement (SOSBK) and a Reservation Agreement?

A reservation agreement is often a three-party contract, and its enforceability can be questionable if it does not contain all legal requirements. An SOSBK is a direct, court-enforceable obligation between the seller and the buyer to enter into a purchase agreement.

2. Can I withdraw from the SOSBK (Future Purchase Agreement) if I do not obtain a building permit?
Only if you have explicitly negotiated this in the contract as a resolutive condition. Otherwise, you are obliged to purchase the land even without a permit; therefore, our attorneys in Prague always keep this condition in mind.

Financing of development projects and loan agreements

Once the land is secured, financing follows in the form of a bank loan, mezzanine financing, or equity.

Banks require robust security and compliance with strict conditions. Errors in a loan agreement can lead to an event of default, allowing the bank to accelerate the entire loan immediately.

Covenants and risks

The bank will stipulate covenants in the contract, such as LTV (Loan to Value) or pre-sale requirements. During construction, unexpected problems may arise, costs may increase, and the developer may breach the budget overrun condition.

If the contract does not contain a resolution mechanism, the bank may stop financing. ARROWS promotes remedy periods and flexible drawdown terms in contracts to ensure the project does not fail due to a formality.

Project Security

The standard is a mortgage on the land and a pledge of receivables from future purchase agreements, plus a pledge of the business interest in the SPV (Special Purpose Vehicle).

Financing based on the "right to build" (právo stavby) is specific, as it is less liquid than land ownership and banks may be more cautious. It is necessary to pre-negotiate that the bank accepts this security and to correctly set up the relationship with the landowner under Czech law.

Risk

How ARROWS (office@arws.cz) assists

Hidden legal defects of the land: Easements, restitution claims, non-compliance with the zoning plan.

Legal Due Diligence: In-depth review of the legal and factual status before purchase in the Czech Republic.

Contractual traps in the SOSBK: Inability to withdraw if the permit is not obtained.

Contract Preparation: Setting up resolutive conditions and developer protection mechanisms.

Suspension of financing by the bank: Breach of covenants, inflexible contract.

Negotiation of loan documentation: Setting up remedy periods and drawdown conditions.

Cost-overrun: Lack of funds for completion.

Equity and debt structuring: Legal setup of relationships with investors and refinancing mechanisms.

Project permit proceedings and authorization processes

The new Czech Building Act introduced a unified project permit proceeding aimed at acceleration, but practice brings challenges associated with digitalization (the Builder's Portal).

Deadlines and process

Czech building authorities have set deadlines for issuing decisions, while the "fiction of a positive binding opinion" from concerned authorities is important and can speed up the process.

For developers, it is crucial to manage the file correctly and respond to objections from participants in the proceedings. ARROWS represents developers in administrative proceedings and handles the effective settlement of objections to prevent obstructions.

get in touch with us,
we’ll take care of it for you

MicroFAQ

1. What is an SPV and why does the bank require it?
An SPV is a company established specifically for a given project, which separates risks from the developer's parent company. The bank thus finances the project purely and has better control over it.

2. How is a budget overrun handled?

Usually, the developer must cover the overrun from their own resources. The contract should have a clear mechanism for how and when these funds are injected to avoid a suspension of loan drawdowns.

Sale of units and taxes

The sale of completed units has significant tax implications, where it is key to distinguish between the VAT regime and corporate income tax under Czech legislation.

VAT on new buildings: Rates and exemptions

For the sale of new apartments and houses, VAT applies, either at a reduced rate of 12% for social housing or the basic rate of 21% for other buildings.

The delivery of a selected real estate item is exempt from tax after 23 calendar months immediately following the month in which it was completed or in which a substantial change occurred. For the developer, it is essential to correctly determine the moment of taxable supply and correctly set up advances during construction.

Building plots and VAT

The Czech VAT Act has its own definition of a building plot, which is broader than in the Building Act.

Sellers often forget to add tax when selling serviced plots. If a utility connection is established on the land and the land is intended for construction, its sale is subject to VAT.

MicroFAQ

1. When must I pay VAT on the sale of an apartment?
You pay VAT on the sale of an apartment if the transfer occurs before the end of the 23rd calendar month following the month in which the building was completed or underwent a substantial change.

2. What about "property flipping"?
When flipping real estate, you become a VAT payer from January of the year following the calendar year in which your domestic turnover exceeded CZK 2,000,000, or on the day following the exceeding of the CZK 2,536,500 threshold in the current year.

3. What is a "substantial change" to a building for VAT purposes?
A substantial change is a modernization that changes the purpose or conditions of habitation, the costs of which (excluding tax) exceed 30% of the property's selling price, triggering a new two-year period for mandatory taxation of the sale.

Declaration of Ownership and final inspection

The sale of units "off-plan" ends with their physical completion and legal definition within the final inspection (kolaudace) and the Declaration of Ownership.

Final Inspection (Kolaudace)

According to the new Czech Building Act, a final inspection permit is issued, for which the builder must prove the building's compliance with the permit. ARROWS assists in resolving changes to the building before completion to ensure the final inspection proceeds smoothly.

Declaration of Ownership

This document divides the building into units and determines co-ownership shares; errors can lead to the rejection of the entry in the Czech Land Registry. The preparation of this document should always be reviewed by an experienced lawyer in cooperation with a surveyor.

get in touch with us,
we’ll take care of it for you

Conclusion

A development project is a legally demanding process involving land due diligence, contractual security, negotiations with the bank, and the final transfer of units.

The attorneys at ARROWS law firm in Prague have experience with dozens of projects across the Czech Republic. We have a team that specializes exclusively in Czech construction and real estate law.

Whether you are just planning a project or dealing with complications during construction, we are ready to help. Contact us at office@arws.cz.

FAQ

1. When should I contact an attorney?

Ideally before signing a reservation agreement for the land. Early due diligence saves the most money.

2. What is the price of legal services?
We offer fixed prices for packages or hourly rates for more complex negotiations. You will always receive a cost estimate in advance. Request a non-binding offer at office@arws.cz.

3. Can you also handle building permits?
Yes, as part of our engineering services, we collaborate with technical supervisors and designers, while our Prague-based attorneys provide legal representation throughout the administrative proceedings under Czech law.

4. Do you represent clients in disputes with construction companies?
Yes, we handle disputes regarding construction defects, failure to meet deadlines, and disputes over additional work (extra costs) within the Czech Republic.

Disclaimer: The information contained in this article is for general informational purposes only and serves as a basic guide to the subject matter. While we strive for maximum accuracy, Czech legislation and its interpretation evolve over time. To verify the current wording of regulations and their application to your specific situation, it is essential to contact ARROWS law firm in Prague directly (office@arws.cz). We assume no responsibility for any damages or complications arising from the independent use of information from this article without our prior individual legal consultation and professional assessment. Every case requires a tailored solution under the Czech legal system, so please do not hesitate to contact us.