When Smaller Czech Construction Projects Trigger Mandatory EIA
EIA can affect even a smaller development project if it falls within a regulated category, is located in a sensitive area or its capacity is later increased. A wrong assessment can delay permitting, force documentation to be revised or stop construction. This article explains when EIA should be checked, how to handle project changes and why a development cannot be artificially split into smaller parts to avoid assessment.

Key takeaways
- Categories I and II: Projects are divided into two categories—some are always subject to EIA, while others go through a screening procedure.
- Below-threshold projects: Even projects below the threshold must be notified if they reach at least 25% of the threshold value and are located in a specially protected area.
- Project changes: Expanding production or the site area may trigger the EIA process if the change reaches the threshold values or 25% of capacity with a significant impact.
- The “salami slicing” method is prohibited: Splitting projects into smaller parts to avoid EIA is unlawful and may result in substantial fines and the revocation of permits.
- Practical risk: Carrying out a project without the required EIA opinion entails the risk of multi-million fines, a construction stop, and the invalidity of follow-on permits.
When and why a project is subject to an Environmental Impact Assessment
Environmental Impact Assessment (EIA) is not just administrative paperwork for mammoth construction projects. Act No. 100/2001 Coll., on Environmental Impact Assessment, clearly determines which projects must undergo this process under Czech legislation. The goal is to ensure that constructions and activities will not have an unacceptable impact on the surrounding environment, water, soil, air, flora, and fauna.
In the Czech Republic, regulation is strict and is based on Directive 2011/92/EU of the European Parliament and of the Council. The purpose of the process is to obtain an objective expert basis for issuing subsequent permits and to ensure that impacts on the environment and public health are taken into account.
Lawyers from the Prague-based ARROWS law firm daily handle projects where investors were mistaken about what the EIA requires. The result often poses a risk of high fines, construction halts, and years of legal disputes. In practice, the rules seem simpler than they actually are, as the law contains a number of exceptions and conditioning factors.
Categorization of projects
The problem begins with how projects are categorized under Annex No. 1 to Act No. 100/2001 Coll. Under Czech legislation, projects are classified into two main categories:
Category I (Projects always subject to assessment): These are major constructions, such as oil refineries, nuclear power plants, motorways, airports with long runways, or large chemical plants. If your project falls under Category I, it must automatically undergo the full EIA process.
Category II (Projects requiring a screening procedure): This includes smaller but still significant projects – breweries, wind power plants, warehouse complexes, shopping centers, or parking lots. Projects in Category II are not automatically subject to a full EIA, but must undergo a screening procedure.
Sub-threshold projects
The third group consists of sub-threshold projects that do not reach the limit values listed in Category II. This includes, for example, smaller warehouses or constructions whose parameters remain below the established thresholds (e.g., a warehouse hall under 6,000 m² of built-up area).
Attention – there is a risk here as well. A sub-threshold project is subject to a screening procedure if:
It reaches at least 25% of the relevant limit value, and
At the same time, it is located in a (National Park, Protected Landscape Area) or its protective zone.
This is precisely where developers make mistakes, as the situation seems simple to them because the project is below the limit. The relevant authority may decide that even a sub-threshold project requires a screening procedure if it meets the conditions and could have a significant impact on the environment.
When a project changes – the risk of a subsequent EIA
One of the greatest risks comes later, when an investor decides to expand, modernize, or technologically modify a project. This is where the concept of a project modification comes into play. If an EIA was issued for the original project and the client now wants to expand the construction, they must pay close attention.
The key rule under Section 4 of the Act is:
Modification reaching the limit value: If the capacity increase itself reaches the limit value according to Annex No. 1, the modification is subject to a screening procedure.
Modification reaching 25%: If the modification has a lower capacity but reaches at least 25% of the capacity of the original project and the authority decides that it may have a significant impact, it must undergo a screening procedure.
In practice, we encounter stories where an investor's project came to a standstill because they expanded operations beyond the tolerance limit without the authorities' knowledge. The result can be a suspension of operations, fines in the millions of CZK, and complex legal proceedings for subsequent permits. The Czech legal team at ARROWS law firm will help you navigate this modification safely.
The salami-slicing method – why it is prohibited
The term "salami-slicing method" refers to a practice where a large-scale project is split into smaller parts, and each part is assessed separately. This practice is prohibited by EU case law as well as decisions of the Czech Supreme Administrative Court.
Practical example: A developer plans a logistics park with a total built-up area of 15,000 m². To avoid a screening procedure, they split the project into three halls of 5,000 m² each and submit an application for each separately over time.
If the authorities prove a functional and spatial connection, they will classify such conduct as bypassing the law. This carries the risk of permit cancellation and the requirement to conduct a retroactive EIA, which is economically and temporally devastating for the investor.
Czech practice is strict regarding the salami-slicing method, and courts repeatedly confirm that functionally or structurally linked constructions must not be assessed in isolation. The decisive factor is the actual functional connection and cumulative impacts. The Prague-based ARROWS law firm will help you ensure that your project is designed in compliance with the law.
The EIA process in practice – what to expect
If you are subject to an EIA process, several phases await you.
Phase 1: Project notification
First, a project notification is submitted to the relevant authority (regional authority or the Ministry of the Environment). The notification is prepared by an authorized person and must contain details about the project, its location, capacity, and anticipated impacts.
Phase 2: Screening procedure
For Category II projects and modifications, a screening procedure takes place, where the authority usually has a 45-day limit to issue a conclusion. The authority examines whether the project could have a significant impact on the environment.
The result is a screening conclusion, which determines whether the project is not subject to further assessment or if it proceeds to a full EIA. Here, the screening of the impact on the Natura 2000 network (Section 45i of the Nature and Landscape Protection Act) also plays a role.
Phase 3: EIA documentation and expert opinion
If an EIA is required, you must arrange for the preparation of the EIA documentation by an authorized person. This is followed by publication, comments from the public and affected authorities, after which the authority commissions an independent expert opinion.
For constructions near Natura 2000 sites, a so-called Natura assessment may also be required. This evaluates the impact on Sites of Community Importance and Special Protection Areas.
Phase 4: Binding opinion
The process culminates in the issuance of a binding EIA opinion by the relevant authority, which is an essential basis for subsequent proceedings. The validity of the opinion is 7 years and can be extended under certain conditions.
Timeframe
The screening procedure usually takes 2–3 months. If it proceeds to a full EIA, the process from notification to the binding opinion typically takes 6 to 12 months, and even longer for complex projects.
Lawyers from the Prague-based ARROWS law firm routinely handle these processes and help prevent delays. Write to us at consultation@arws.cz.
Table of key risks and how ARROWS helps you
Risks and sanctions | How ARROWS helps (consultation@arws.cz) |
Fine for construction without a permit: Implementing a construction without the relevant permit (due to a missing EIA) can result in a fine of up to CZK 2 to 10 million under the Building Act (depending on the type of construction). | ARROWS will check if your project requires an EIA and ensure legal supervision over the entire process. |
Cancellation of permit: If a permit was issued without a mandatory EIA, it can be cancelled by a court. Construction must stop, and there is a risk of an order for its removal. | ARROWS lawyers will represent you in negotiations with authorities and minimize procedural errors. |
Salami-slicing method: Detecting purposeful splitting of a project leads to a requirement for a new assessment of the whole and potential sanctions for bypassing the law. | We will help set up the project so that it complies with the law and does not face allegations of the salami-slicing method. |
Financing blockade: For larger projects, banks require confirmation of EIA compliance (ESG standards). Without a valid opinion or screening, you may not obtain a loan. | We will prepare a legal memorandum confirming the correctness of the procedure for the bank or investor. |
Specific examples – when you will be subject to an EIA
To better understand where the line is drawn, let's look at the limits under Annex No. 1 to Act No. 100/2001 Coll. under Czech legislation. These limits are crucial for developers.
Commercial and warehouse complexes
For commercial complexes and shopping centers, as well as warehouse complexes, a limit of 6,000 m² of built-up area applies. If you have a hall project with 5,000 m², you are generally not subject to a mandatory screening procedure, provided you are not in a protected area.
Parking lots and garages
A separate category consists of parking lots or garages, where the limit is set at 500 parking spaces. If you are building an office building with garages for 550 cars, you fall under the EIA, even if the building itself does not meet the limit.
Residential development
Apartment buildings themselves do not have a direct area limit set in the law like warehouses, but they can fall under so-called urban development projects. The limit here is often 5 hectares of project area, but beware of locations in protected areas.
Wind power plants
For wind power plants, the limit is very low; sources with a capacity higher than 500 kWe or a tower height exceeding 35 meters are subject to a screening procedure. In essence, every modern industrial wind turbine is subject to this limit.
Modifications in industrial operations
If you have a manufacturing plant and want to increase capacity, the rule on modifications applies. Increasing capacity above the limit or by more than 25% (if the limit is already exceeded or if the modification has a significant impact) triggers the process.
Obligation to verify – how to proceed safely
If you plan any significant construction project, you should conduct a legal audit even before you start spending large sums on a designer.
Step 1: Identify your project
Clarify the exact parameters, such as built-up area in m², number of parking spaces, production capacity, or height of the construction.
Step 2: Compare with Annex No. 1 to the Act
Compare your project with the limits in Annex No. 1 to Act No. 100/2001 Coll. and find out whether you fall under Category I, Category II, or if you are below the limit.
Step 3: Consider sub-threshold projects and location
If you are below the limit, verify whether you are located in a specially protected area (PLA, NP) or a protective zone. If so and you reach 25% of the limit, you must submit a notification of a sub-threshold project.
Step 4: Contact a lawyer
Before submitting an application to the authority, consult the procedure with experts. The Prague-based ARROWS law firm will conduct a legal assessment for you and recommend a strategy.
Unified Environmental Binding Opinion (JES)
With the entry into force of the new Building Act and the Unified Environmental Binding Opinion Act (No. 148/2023 Coll.), the processes are integrated. The Unified Environmental Binding Opinion (JES) consolidates a number of previously separate administrative acts in the environmental field.
If your project is subject to an EIA, the output of the EIA process (binding opinion) serves as a binding basis for issuing the JES, or is integrated into it. Lawyers from the Prague-based ARROWS law firm will help you navigate the JES system and the new building permit proceedings.
Detailed overview table (Category II – screening procedure)
Type of project (Annex No. 1) | Limit value (requires screening procedure) | Note |
Commercial complexes and shopping centers | 6,000 m² of built-up area | Point 10.6 |
Warehouse complexes | 6,000 m² of built-up area | Point 10.6 |
Parking lots or garages | 500 parking spaces | Point 10.15 |
Wind power plants | Capacity > 0.5 MW or height > 35 m | Point 3.2 |
Recreational and sports complexes, hotels | Built-up area over 1 ha (in a protected area) | Point 10.8 (outside protected area from 2 ha) |
Wastewater treatment plants | Capacity from 10,000 to 100,000 PE | Point 1.9 (over 100k is Cat. I) |
Mining of mineral resources | Area from 5 to 25 ha | Point 2.5 (over 25 ha is Cat. I) |
Project modifications | Reaching the limit or +25 % of capacity/limit | Under Section 4 of the Act |
Conclusion
Environmental Impact Assessment plays a key role in the permitting process, as you cannot obtain a building permit without a proper EIA opinion. You thus risk high sanctions and the devaluation of your investment.
The rules are not trivial, and bypassing the law does not pay off. The boundaries between categories, the rules for project modifications, and the specifics of protected areas require expert knowledge.
Lawyers from the Prague-based ARROWS law firm handle EIA projects every day and we know where the most common mistakes lie. The Czech legal team at ARROWS law firm handles EIA projects every day. If you are planning a construction project, do not hesitate to contact us at consultation@arws.cz.
About the author
Disclaimer:
The information contained in this article is for general informational purposes only and serves as a basic guide to the issue as of 2026. Although we strive for maximum accuracy, laws and their interpretation evolve over time. We are ARROWS Law Firm, a member of the Czech Bar Association (our supervisory authority), and for the maximum security of our clients, we are insured for professional liability with a limit of CZK 350,000,000. To verify the current wording of the regulations and their application to your specific situation, it is necessary to contact ARROWS Law Firm directly (consultation@arws.cz). We are not liable for any damages arising from the independent use of the information in this article without prior individual legal consultation.