Skip to content

Building Permits for Major Development Projects 2026

How the Amendment Will Accelerate Construction Permitting

An amendment to the Czech Building Act, approved by the Chamber of Deputies on July 10, 2026, changes the very architecture of the permitting process for large residential projects: projects with a floor area of 10,000 m² or more are moved to the reserved constructions regime with a single, centralized procedure, without an ordinary appeal, and with limited judicial review. This article discusses which projects will fall under the new regime, where exactly time is supposed to be saved — and what the developer will pay for it in terms of claims and risks.

The illustrative photo depicts experts discussing the impacts of the new Construction Act.

The essentials in six points:

A building or complex of buildings with a predominantly residential function and a total floor area of 10,000 m² or more will now fall under the designated construction regime. The term “complex of buildings” is key—even a phased project consisting of smaller buildings may exceed this threshold.
Such a project will be approved by a central government agency in a single proceeding—rather than by the locally competent building authority and dozens of binding opinions. Moreover, the construction of designated structures is, by law, in the public interest.
No appeal may be filed against a decision regarding a designated construction project—the entire appeals process, which currently takes months or even years for large projects, is eliminated. The only recourse remaining is an administrative lawsuit, which must be filed within one month.
Binding opinions are being streamlined and standardized—the review of an opinion is subject to a 30-day deadline, after which it is deemed approved; the agency will not consider portions of the opinion that exceed its jurisdiction; and issues resolved by the zoning plan will not be reopened during the proceedings.
Judicial review is being narrowed—the court is to assess the grounds for the complaint only to the extent that they directly infringe upon the plaintiff’s rights, and, when revoking a permit, to weigh the plaintiff’s harm against the developer’s harm and the public interest.
The amendment is not yet law—it is headed to the Senate, and the provisions on designated structures and restrictions on review are among the provisions likely to face a constitutional challenge. Base your strategy on both scenarios.
ARROWS law firm

Which projects will fall under the new regime: a close reading of the 10,000 m² threshold

According to Parliamentary Print 67, a building for mass housing is defined as a building or a set of buildings with a predominant residential function and a total floor area of 10,000 m² or more. Every word of this definition has practical consequences for a developer. ‘A set of buildings’ means that even a project divided into several smaller buildings or phases can exceed the threshold—so, a deliberate division of a project to stay below the limit may not hold up.

‘Predominant residential function’ means that a mixed-use project with a majority of retail or office space will not fall under this regime, even if the residential part itself exceeds 10,000 m². And ‘total floor area’ is calculated for the entire project, not just for the residential function.

For projects near the threshold, the volume study thus becomes a legal document: a difference of a few hundred square metres will decide whether the project is permitted by the local building authority under the standard regime, or by the central authority under the designated construction regime. Both options have their advantages—and the choice can, in justified cases, be a legitimate subject of design optimisation. We summarise the broader context of the reform, including the timeline for the new system of authorities, in our main article Accelerated Permitting for Development Projects: What the Amendment to the Building Act Brings.

Frequently Asked Legal Questions about the 10,000 m² Threshold

1. Will large office or logistics complexes also fall under the designated construction regime?

No. The new category is aimed exclusively at buildings with a predominant residential function. Large non-residential projects remain under the standard regime—unless they qualify as another type of designated construction under Annex No. 3 of the Building Act (typically transport or energy infrastructure).

2. How is the floor area calculated for the threshold?

The decisive factor is the total floor area of the building or set of buildings, i.e., for the entire project, including non-residential parts. For projects near the threshold, we recommend having the calculation legally verified before finalising the design—the newly expanded preliminary information procedure can also be used for this purpose.

3. Can we voluntarily opt for the designated construction regime even if we are below the threshold?

No. According to the approved text, the regime follows directly from the statutory parameters of the project and is not the developer's choice—below the threshold, the project proceeds under the standard joint procedure at the territorially competent authority.

ARROWS law firm

A single procedure at a central authority—and why it's more than just a change of address

Designated constructions are currently permitted under the Building Act (Act No. 283/2021 Coll.) by the specialised Transport and Energy Building Authority—this includes motorways, railways, and energy infrastructure. The amendment transfers this model to large residential projects: they are to be permitted by the new Office for Territorial Development in a single procedure that consolidates the agenda of the previously involved authorities.

For a developer, this means three practical shifts: a specialised authority with a unified methodology instead of 638 local practices, an end to dependence on relationships with a specific municipal council (and the associated systemic bias)—and a single counterparty instead of dozens.

The biggest time saver: the appeal phase is eliminated

For standard constructions, the amendment will end lengthy appeal processes, and the superior authority will have to issue a final decision. For designated constructions, however, the approved text goes further: an administrative appeal (rozklad) against the central authority's decision is not permissible. The procedure is effectively single-instance—a phase that currently often adds a year or more to large projects will disappear from the process entirely. The only way to challenge a permit (or its refusal) is through an administrative action (judicial review), for which the Building Act sets a one-month deadline from the notification of the decision—a deviation from the general two-month deadline under the Code of Administrative Justice (Act No. 150/2002 Coll.).

However, the single-instance nature is a double-edged sword. An error by the authority, which can currently be corrected cheaply and quickly on appeal, will now only be resolvable in court—and the same applies to an error in the developer's application documents that the authority incorporates into its decision. The quality of the application and documentation at the outset will therefore not just be a matter of speed for designated constructions, but a matter of the legal certainty of the outcome itself.

Second saver: binding opinions under control and the zoning plan as a settled issue

Under the approved text, the number of binding opinions is significantly reduced, and the remaining ones are given firm rules: the review of an opinion by a superior body is capped at 30 days, and if this deadline passes without action, a fiction of approval applies. At the same time, the building authority is not to consider parts of statements where the relevant body exceeds its competence or reopens issues already resolved in the zoning plan documentation—furthermore, in developable areas, there is a rebuttable presumption that a project consistent with the zoning plan is permissible. The environmental agenda is concentrated in the EIA process under Act No. 100/2001 Coll., which will now be able to integrate other opinions at the developer's request.

Important news for projects already in progress: according to the transitional provisions, opinions and decisions of the relevant authorities issued before the new authorities are established will retain their legal effect, and if the developer submits them, the authority will not reassess the public interests protected by them.

Third saver: objections and judicial review with tighter limits

Participants' objections will have to be justified and specific—the participant must state the extent to which their rights are affected, otherwise the objection will be disregarded. Blanket disagreements without legal basis will therefore not delay the procedure. In the subsequent judicial review, the court is to assess the points of action only to the extent of the alleged direct infringement of the plaintiff's rights and, new, also to weigh the consequences: even a well-founded action should not lead to the annulment of the permit if the annulment would cause disproportionately greater harm to other persons or the public interest than the dismissal of the action would cause to the plaintiff.

Together with the existing option for the court to directly amend the contested decision, this is a significant shift towards the stability of a once-issued permit. However, these provisions are also the most sharply criticised part of the amendment—environmental organisations, some municipalities, and the Public Defender of Rights have warned in their comments about the weakening of judicial protection for neighbours and the public.

If the Senate does not change the text, a motion to repeal these provisions before the Constitutional Court can be expected. A prudent development strategy therefore works with the advantages of the new review process but does not build on them—a permit that can withstand even a standard review is the only truly safe investment.

Mechanism

How it works and what it means for the developer

Designated construction regime (from 10,000 m²)

The procedure is led by the central Office for Territorial Development, and the construction is assessed as a project in the public interest. The developer benefits from a unified procedure instead of varying local practices, but it is necessary to correctly assess whether the project falls into this regime already in the preparation phase.

Exclusion of administrative appeal (rozklad)

It is not possible to file an administrative appeal (rozklad) against a decision on a designated construction. This shortens the procedure by months or even years, but at the same time, any error can lead directly to judicial review, thus increasing the importance of high-quality project documentation.

End of the appeal ‘ping-pong’ (other constructions)

The appellate body must decide itself and cannot return the case for a new hearing. The procedure thus gains a predictable end even for projects that are not designated constructions.

Reduction and disciplining of binding opinions

The number of opinions is limited, their review is time-bound, and a fiction of approval can apply in case of inaction. This reduces a frequent source of hidden delays, and issues already resolved in the zoning plan are not reopened.

Justified objections

Objections without specific justification or without stating the affected rights are disregarded. Obstructionist or general objections thus lose their ability to delay the procedure.

Narrowed judicial review

The court reviews only the specifically raised points of action and decides within short deadlines. Issued permits are more stable, although some rules may be subject to constitutional review.

ARROWS law firm

What to do with your project right now

Three steps are worthwhile regardless of the outcome of the debate in the Senate. Have a legal assessment conducted to determine whether and which projects in your portfolio will fall under the designated construction regime—including borderline cases and phasing, where every word of the definition matters.

Map the timing of your applications against the reform's timeline and transitional provisions, so that the choice of regime is a conscious decision, not an accident. And review your work-in-progress documentation from the perspective of a joint, single-instance procedure, where defects can no longer be corrected along the way—and each one will go straight to court.

We deal with these issues in our construction law practice every day. Want to know which regime your project will fall under and what it will do to your schedule? Email us the basic parameters of your project at consultation@arws.cz—within a few days, you will receive a specific answer, including recommendations on timing.

Frequently Asked Questions

1. Will large office or logistics complexes also fall under the designated construction regime?

No. The new category is aimed exclusively at buildings with a predominant residential function. Large non-residential projects remain under the standard regime—unless they qualify as another type of designated construction under Annex No. 3 of the Building Act (typically transport or energy infrastructure).

2. How is the floor area calculated for the threshold?

The decisive factor is the total floor area of the building or set of buildings, i.e., for the entire project, including non-residential parts. For projects near the threshold, we recommend having the calculation legally verified before finalising the design—the newly expanded preliminary information procedure can also be used for this purpose.

3. Can we voluntarily opt for the designated construction regime even if we are below the threshold?

No. According to the approved text, the regime follows directly from the statutory parameters of the project and is not the developer's choice—below the threshold, the project proceeds under the standard joint procedure at the territorially competent authority.

4. Does the 10,000 m² threshold also include the non-residential part of the project?

The threshold refers to the total floor area of the building or set of buildings, but the condition is a predominant residential function. For mixed-use projects, the ratio of functions is therefore decisive—and it is precisely for these that we recommend a legal assessment before the design is finalised.

5. Can we divide the project into phases to avoid the threshold—or, conversely, to exceed it?

The definition speaks of a 'building or set of buildings', so a deliberate division of a single, functionally connected project to stay below the threshold carries a significant risk that the authority will assess it as a whole. Legitimate design optimisation is possible, but it must have a real urban planning and operational basis—this is a matter for specific assessment, not a general guide.

6. Does the exclusion of administrative appeal (rozklad) mean that no one can challenge the permit?

No—neighbours and other affected parties can file an administrative action (judicial review), as can the developer against a refusal. However, the administrative appeal phase is eliminated, and judicial review has narrower limits. Critics see this combination as a weakening of legal protection, and a test before the Constitutional Court can be expected.

7. By how much will the permitting process realistically be shortened?

No one can give a serious number today—it depends on the staffing of the new authorities and how quickly practices stabilise. Structurally, the amendment removes the phases that currently take the longest: the appeal merry-go-round, chasing down opinions, and reopening issues from the zoning plan. The potential is in the order of many months; its realisation will only be shown in the first year of operation.

8. What will happen with the EIA—will it also be accelerated?

The EIA remains a separate process under Act No. 100/2001 Coll., but it is now intended to function as the sole environmental interface: the unified environmental opinion is abolished, and the EIA will be able to integrate other opinions at the developer's request. For large projects subject to assessment, this means a simpler process architecture, not its abolition.

9. Is any of this in effect yet?

No. The Chamber of Deputies approved the amendment on July 10, 2026, followed by the Senate and the President. The rules described are based on the version approved by the Chamber of Deputies and may still change; we recommend finalising your strategy only after the law is officially promulgated.

10. We have a project in progress—should we wait for the new regime?

It depends on the preparation phase, the size of the project, and the opinions already obtained—which, according to the transitional provisions, will retain their effect even under the new regime. We discuss typical scenarios and decision-making criteria in a separate article on the timing of the application.

DO YOU HAVE MORE QUESTIONS? GET IN TOUCH

ARROWS law firm

About the author

JUDr. Jakub Dohnal, Ph.D., LL.M.
JUDr. Jakub Dohnal, Ph.D., LL.M.

Associate, managing partner

Jakub Dohnal is a founding member of our law firm and our entire consulting group. He is primarily involved in real estate development and advising on the complex setup of commercial projects.

Disclaimer:

The information contained in this article is for general informational purposes only and serves as a basic orientation on the issue under Czech legislation as of 2026. Although we strive for maximum accuracy of the content, legal regulations and their interpretation evolve over time. We are ARROWS, a Prague-based law firm, an entity registered with the Czech Bar Association (our supervisory authority), and for the maximum security of our clients, we are insured for professional liability up to a limit of CZK 400,000,000. To verify the current wording of regulations and their application to your specific situation, it is necessary to contact ARROWS law firm directly (konzultace@arws.cz). We are not liable for any damages arising from the independent use of information from this article without prior individual legal consultation.