Reducing disputes in real estate development
Project sales contracts
The sale of a real estate development project is not a straightforward transaction. The buyer will thoroughly review the construction, rely on the promised specifications, and have high expectations. If reality differs from what you promised in the contract, or if the documentation contains inaccuracies, you can expect a series of claims, disputes, and potential court proceedings. In this article, we will show which key elements to focus on and which wording and mechanisms will help you reduce the risk of future disputes.

- The purchase agreement must precisely define all essential parameters of the project (size, location, materials used, construction works, fit-out) and must match the actual condition—vague wording leads to disputes.
- Without clearly defined and documented records of defects and their remediation, you face lengthy court proceedings and the risk of liability for defects that were apparent upon acceptance.
- Agreed quality guarantees and their time limits must be realistic and substantively defined, including a clear procedure for reporting claims; overly long or vague guarantees increase your legal and financial risk. Statutory time limits for asserting rights arising from defects (liability for defects) are set for buildings at .
- The handover and acceptance protocol for the building is decisive evidence of its condition; if the buyer refuses to sign it, this may weaken your position in a later dispute regarding the condition of the property at the time of acceptance.
- Proven risk-reducing techniques: a list of defects, security mechanisms (e.g. , a contractual penalty for breach of the buyer’s obligations), clear exclusions and limitations of liability (in compliance with the law), agreed dispute resolution procedures.
What is worth including in a purchase agreement: key points
Accurate description of the building and individual elements
The more specifically you describe what you are selling, the less room there is for interpretation. The buyer cannot later demand higher quality if you defined precise parameters in the agreement.
What to include specifically:
- The floor area of the building and each unit being sold in square metres (with reference to the project documentation, the owner’s declaration or a geometric plan, or an expert report, as applicable).
- The location and orientation of the property (relevant floors, exposure).
- Materials and technologies used (type of façade, windows, heating system, water supply), including references to specific technical standards (ČSN, EN) or suppliers’ technical specifications. For development projects, it is worth checking whether the description of materials and technologies also corresponds to the permitting documentation and as-built/implementation documentation, which falls within development and construction law.
- Interior description—colours, type of flooring, bathroom and kitchen fit-out, etc.
- A list of immovable and movable items included in the sale (parking spaces, cellars, front gardens, built-in appliances, inventory, etc.).
- The technical legal term here is: quality specification—i.e., a precise definition of what is considered proper performance, not what is considered deficiencies (defects). Defects are defined in the Czech Civil Code as deviations from agreed or usual characteristics.
Avoid general wording such as “the building has been inspected”, “it is in good condition” or “it will be carried out according to the project documentation”. The buyer will simply ignore such sentences and later claim they understood something else.
Clear records of defects and their remediation
If there are any deficiencies at the final handover of the building—cracks in plaster, a non-functioning socket, damp on a wall—they must all be documented. Without this documentation, it is difficult to defend yourself later.
How to do it properly:
- Already during construction (or at the latest before handover), prepare a list of defects (inspection report, report on identified defects). It should include photographs, exact locations, a description of the defect, and an estimate of the time required for repair.
- The list of defects should form part of the handover protocol or be attached to it, so there is no doubt as to which defects were known at the time of handover.
- Key point: Set a clear deadline by which the defect must be remedied, and who will bear the costs. For setting enforceable deadlines and penalties, including linkage to the handover protocol, practical examples relating to inflation clauses in contracts for work may also be useful, as they often affect the cost side of defect remediation. If the buyer accepts the building “with knowledge of defects” and agrees that they will not be remedied or will be remedied later, this should be expressly stated in the handover protocol.
- If certain defects cannot be remedied (for example, an accepted structural or aesthetic deviation from the standard), this fact should be included in the agreement or the handover protocol so that the buyer cannot later claim they were unaware of it.
Our attorneys in Prague at ARROWS can help you draft the wording of a list of defects that is factual, clear, and legally robust.
Warranties and their scope
This is a common mistake. Developers set overly long and vague quality warranties without properly defining them, while buyers believe they are entitled to decades of “free” repairs. It is important to distinguish between statutory liability for defects and a contractually agreed quality warranty.
Correct setup:
- Liability for defects (statutory): The Czech Civil Code provides that the buyer is entitled to notify a hidden defect in a building within five years from acquiring title. This is a statutory period for notifying a defect, not a quality warranty in the sense of guaranteeing defect-free performance for the entire period. The buyer must notify the defect without undue delay after they could have discovered it.
- Warranty period (quality warranty agreed contractually): This can be agreed contractually and typically relates to specific parts of the building or the works. If the developer decides to provide a quality warranty, its duration and scope must be clearly defined. A commonly agreed quality warranty is in the range of 24 to 36 months for construction works and supplies. Long-term warranties (e.g., 60 months) increase your risk; choose a more realistic period consistent with the service life of materials and equipment.
- Scope of the quality warranty: Clearly define what is warranted (e.g., “construction works carried out at least in accordance with applicable ČSN and EN technical standards, consistent with the design documentation and the purchase agreement”) and what is not (e.g., wear and tear, normal maintenance, physical damage caused by the buyer, defects caused by unprofessional intervention by a third party, defects caused by force majeure).
- Reporting procedure: The buyer must report a defect without undue delay after discovering it, but no later than in accordance with the Czech Civil Code (5 years for a hidden defect in a building, unless a different notification period is agreed in the contract). The contract may set a reasonable period for notifying an apparent defect from the time it is discovered; however, failure to comply must not lead to an automatic “loss of defect rights” for hidden defects contrary to law. It is advisable to specify written notice, including delivery requirements and contact details. This condition protects you from a buyer waiting a year and then suddenly alleging a dozen “old” defects.
- Responsibility for rectification: Explicitly state that you or your contractor will remedy the defect at your cost, and that the buyer is not entitled to hire their own tradesperson and invoice you, unless you fail to remedy the defect within a reasonable time or you have given prior consent to such a procedure.
Technical legal term: **quality warranty** constitutes the legal basis on which the seller’s liability for the agreed quality of the предмет of sale rests for a certain period. If you do not set it properly in the purchase agreement, you will be liable under the default rules of the Czech Civil Code, which is typically less predictable for you.
Handover and acceptance protocol for the building
This protocol is not just a formality. It is a legal document that determines the moment when the risk of damage to the item passes to the buyer and when the building is accepted with all its characteristics, including apparent defects.
Specific steps:
- The protocol is signed by your representative, the construction supervisor (if present), and the buyer (or their representative).
- It must include: the date and time of handover, an inventory list, a list of known defects (with reference to the defect list), confirmation of utilities/functions (water, electricity, heating, drainage), and meter readings (electricity meter, water meter, gas meter).
- If the buyer refuses to sign the standard protocol (e.g., because they believe the building is defective and the defects were not stated in the protocol), it is crucial to properly document the situation (e.g., a record of refusal to accept, presence of witnesses). In such a case, we do not recommend handing over the keys until the dispute is resolved or until the buyer unjustifiably refuses acceptance. Resolve the disagreement under the contract (e.g., by an independent expert assessment).
- Even if the buyer signs the protocol, this does not deprive them of legal claims arising from liability for hidden defects of the sold item under the Czech Civil Code. However, signing the protocol significantly weakens their position when asserting claims for apparent defects, as they confirmed that they accepted the building in that condition.
Attorneys from ARROWS advokátní kancelář will prepare the protocol in a way that is legally relevant and safe for both parties.
Additional risk-reducing measures: practical mechanisms
Escrow account
Sometimes, in larger transactions, a model is used where the buyer pays a certain percentage of the price (typically 5–10%) into an escrow account held by a notary, attorney, or bank. These funds are released only after the agreed warranty period has elapsed (with no claims) or are used to cover the costs of remedying defects. Such a model reduces your risk of the buyer increasing the number of artificial claims at the last minute.
Contractual penalty and limitation of liability
The purchase agreement should include:
- Contractual penalty: A contractual penalty may be agreed for a breach of specific contractual obligations of the buyer (e.g., late payment of the purchase price, delay in acceptance, unauthorised use of the property before payment of the purchase price). A penalty for the mere reporting of a defect that the buyer caused themselves, or that was listed in the original defect list, is legally problematic and likely unenforceable. Instead, it is more appropriate to agree reimbursement of costs associated with an unjustified claim.
- Limitation of liability: It is possible to expressly agree a cap on the amount of your liability for damages (e.g., beyond agreed quality warranties or statutory liability for defects), for example as a certain percentage of the purchase price, provided such limitation is not contrary to (e.g., liability for intentionally caused damage or damage caused by gross negligence cannot be limited, nor can it conflict with consumer protection rules). The limitation of liability should be drafted clearly and with regard to the specific risks.
These clauses are legally valid in the Czech Republic provided they are not “unreasonably detrimental” to the other party (especially in the case of a consumer) and are not contrary to good morals or mandatory provisions of the Czech Civil Code. In developer projects in B2B relationships they are common and accepted, but their use is limited in consumer contracts.
Risk table: typical issues and how to address them
|
Possible issues |
How ARROWS can help (consultation@arws.cz) |
|
Vague description of the building in the purchase agreement – The buyer later claims it should have been of better quality or a different size. A dispute arises as to what was actually sold. |
The attorneys at ARROWS, a Prague-based law firm, will prepare a detailed technical annex to the agreement with an exact description of all parameters, materials and fittings, with references to the applicable documentation. This eliminates room for interpretation. |
|
Missing or incomplete list of defects – The buyer later claims they did not notice the defect upon handover. Without documentation, it is difficult to defend against claims relating to apparent defects. |
The attorneys at ARROWS, a Prague-based law firm, will prepare a formal handover protocol and a list of defects with an exact description and location of apparent issues. This protocol then serves as evidence of the condition of the building at the time of handover. |
|
Undefined or overly long quality warranties – There is a risk that the buyer will bother you with “complaints” long after the sale, moreover contrary to the statutory rules on liability for defects. |
ARROWS, a Prague-based law firm, will set realistic and legally safe warranty terms (agreed quality warranties typically 24–36 months), a clear defect reporting procedure, and a list of what is not covered by the quality warranty (wear and tear, maintenance, buyer error), and will highlight the statutory 5-year period for notifying a hidden defect in a building under the Czech Civil Code. |
|
The buyer refuses to sign the handover protocol or subsequently interprets it differently – You lose legal evidence of the condition in which the buyer took over the building, or a dispute arises over the handover. |
The attorneys at ARROWS, a Prague-based law firm, will ensure that the protocol is drafted correctly from a legal perspective, is formally delivered to both parties, and is consistent with the purchase agreement. If the buyer refuses to sign, they can represent you in resolving the dispute. |
|
Court dispute over the quality of the building or breach of defect-related obligations – Conducting litigation requires expert representation, expert opinions and significant financial costs. |
ARROWS, a Prague-based law firm, represents you in court proceedings, communicates with the court, prepares documentation and proves—based on the purchase agreement and protocols—that you have fulfilled your obligations, and can also help with an efficient resolution of the dispute. |
Final summary
The sale of a development project requires an investment in legal protection. If you prepare the purchase agreement carefully, you will have strong tools against future complaints. There are four key elements:
- An accurate, detailed description of the building and its parameters.
- A documented list of apparent defects, which becomes part of the agreement or the handover protocol.
- Realistically defined quality warranties (if agreed) with a clear reporting procedure and respect for statutory liability for defects.
- A legally formalised handover protocol for the building, signed by the buyer.
If it seems to you that preparing all of this is time-consuming, bear in mind that the investment in a properly drafted agreement is an order of magnitude lower than the costs of court litigation.
The attorneys at ARROWS, a Prague-based law firm, have experience with dozens of development projects and know the typical pitfalls and how to avoid them. Specialists at ARROWS, a Prague-based law firm, will help you draft the agreement, review it from a risk perspective, and prepare you for negotiations with the buyer.
If you want to minimise the risk of future disputes and complaints, contact consultation@arws.cz to request legal advice for your specific transaction.
Read also:
- Buying Brownfields in Czechia: Environmental Liabilities and Duties in 2026
- Zoning Plan Amendments Under the New Building Act: Process and Pitfalls
- How to Submit Comments on Czech Zoning Plan Changes Under the New Building Act
- Radon in New Buildings: Legal Duties, Liability and Sanctions Under Czech Law
- Eviction order 2026: How to get rid of a delinquent tenant faster
About the author
Disclaimer:
The information contained in this article is for general informational purposes only and serves as a basic guide to the issue as of 2026. Although we strive for maximum accuracy, laws and their interpretation evolve over time. We are ARROWS Law Firm, a member of the Czech Bar Association (our supervisory authority), and for the maximum security of our clients, we are insured for professional liability with a limit of CZK 400,000,000. To verify the current wording of the regulations and their application to your specific situation, it is necessary to contact ARROWS Law Firm directly (consultation@arws.cz). We are not liable for any damages arising from the independent use of the information in this article without prior individual legal consultation.